Thursday, October 29, 2009

Campus Center – Rockville Renovation

FIP Informational BLOG "Link"

  • Jan. 2009 / Aug. 2009 – Develop IT project requirements and plan IT implementation project (Finalize requirements, finalize SOW, build team, etc)
  • Jul. 2009 / Jan. 2010 – Participate in construction activities (monitoring, inspections, and corrections)
  • Oct. 2009 / March 2010 – IT in-building implementation activities (installation, integration and testing of network, telephone, audio visual, Wi-Fi, and desktop equipment)
  • TBD – Client move in
  • TBD Opening

Science Center (SC) – Rockville New Building
FIP Informational BLOG "Link"

  • Jan. 2009 / Jan. 2010 – Develop IT project requirements and plan IT implementation project (Finalize requirements, finalize SOW, build team, etc)
  • Jul. 2009 / Dec. 2010 – Participate in construction activities (monitoring, inspections, and corrections)
  • Jan. 2010 / Jul. 2010 – IT pre-building access implementation activities (procurements, deliveries, configuration burn-in,)
  • Jul. 2010 / Jan. 2011 – IT in-building implementation activities (installation, integration and testing of network, telephone, audio visual, Wi-Fi, and desktop equipment)
  • Nov. 2010 / Mar. 2011 – Client move in
  • Spring 2011 Opening

Science East Renovation – Rockville Campus
FIP Informational BLOG "Link"

  • Jul. 2009 / Dec. 2009 – Participate in development, participates in planning, budget development, & construction planning (meetings and requirements development) – ensure appropriate IT groups are consulted. SCIENCE EAST ONLY
  • Sept. 2009 / Jul. 2010 – Develop IT project requirements and plan IT implementation project (finalize requirements, finalize SOW, build team)
  • May 2010 / Dec. 2011 - Participate in construction activities (monitoring, inspections, and corrections)
  • Jan. 2011 / Jul. 2011 – IT pre-building access implementation activities (procurements, deliveries, configuration burn-in,)
  • Jul. 2011 / Jan. 2012 – IT in-building implementation activities (installation, integration and testing of network, telephone, audio visual, Wi-Fi, and desktop equipment)
  • Nov. 2011 / Mar. 2012 – Client move in
  • Spring 2012 Opening

Science West Renovation – Rockville Campus
FIP Informational BLOG "Link"

  • Jan. 2010 / Jul. 2010 – Participate in development, participates in planning, budget development, & construction planning (meetings and requirements development) – ensure appropriate IT groups are consulted. SCIENCE WEST ONLY
  • Jul. 2011 / Dec. 2011 – Develop IT project requirements and plan IT implementation project (finalize requirements, finalize SOW, build team)
  • May 2011 / Dec. 2012 - Participate in construction activities (monitoring, inspections, and corrections)
  • Jan. 2012 / Jul. 2012 – IT pre-building access implementation activities (procurements, deliveries, configuration burn-in,)
  • Jul. 2012 / Jan. 2013 – IT in-building implementation activities (installation, integration and testing of network, telephone, audiovisual, Wi-Fi, and desktop equipment)
  • Nov. 2012 / Mar. 2013 – Client move in
  • Spring 2013 Opening

The Commons (CM) Renovation - East Takoma Park
FIP Informational BLOG "Link"

  • In-Progress - Participating in construction activities (monitoring, inspections, and corrections)
  • In-Progress - Manage the IT Implementation project
  • Winter 2009/Spring 2010 Move ins and Opens spring 2010

Bioscience Education Center (BE) - Germantown New Building
FIP Informational BLOG "Link"

  • In-Progress - Participate in programming review, design, & pre-construction activities
  • 2010/2011 – Develop IT project requirements and plan IT implementation project (finalize requirements, finalize SOW, build team etc)
  • 2010 - 2011 – Participate in construction activities (monitoring, inspections, and corrections)
  • 2011 - 2012 – Implement, procurement, and manage the IT Implementation project

West Campus Garage (WG) West Takoma
FIP Informational BLOG "Link"

  • On-going – Participate in construction activities (monitoring, inspections, and corrections)
  • On-going - Implement, procurement, and manage the IT Implementation project
  • 2009 – Client occupancy/use anticipated in fall 2009/spring 2010.

Rockville Data Center Retrofit/Renovation - Rockville Campus

(Blog to be created)

  • 2009 - Participating in planning and design activities
  • TBD - Participate in construction activities (monitoring, inspections, and corrections)
  • TBD – Implement, procurement, and manage the IT Implementation project

Science & Applied Studies (SA) Renovation # 1 - Germantown Campus
FIP Informational BLOG "LINK"

  • 2010 - 2011 Participate in planning and design activities
  • 2012 - Participate in construction activities (monitoring, inspections, and corrections)
  • 2013 – Implement, procurement, and manage the IT Implementation project

Student Services Center (SV) - Rockville New Building
FIP Informational BLOG "Link"

  • In-Progress - Building Programming and Planning
  • 2009 - 2010 - Program verification
  • 2010 - 2011 - Participate in design and construction documents
  • 2011 - 2012 – Develop IT project requirements and plan IT implementation project (finalize requirements, finalize SOW, build team etc)
  • 2012 - 2014 - IT Implementation
  • 2014 - Client Occupancy

Health Sciences Center (HC) Renovation – Takoma Park Nursing Expansion and Movement of WFD to CF.
FIP Informational BLOG "Link"

  • 2009 – Participate in development, participate in planning, budget development, & construction planning (meetings and requirements development) – ensure appropriate IT groups are consulted
  • 2009 –Develop IT project requirements and plan IT implementation project (finalize requirements, finalize SOW, build team etc)
  • 2009 - 2010 – Participate in construction activities (monitoring, inspections, and corrections)
  • 2009 - 2010 – Implement, procurement, and manage the IT Implementation project

The Morris & Gwendolyn Cafritz Foundation Arts Center (CF) Renovation

Takoma Park Movement of WFD to CF. FIP Informational BLOG "Link"

  • 2009 – Participate in development, participate in planning, budget development, & construction planning (meetings and requirements development) – ensure appropriate IT groups are consulted
  • 2009 - 2010 –Develop IT project requirements and plan IT implementation project (finalize requirements, finalize SOW, build team etc)
  • 2009 - 2010– Participate in construction activities (monitoring, inspections, and corrections)
  • 2009 - 2010 – Implement, procurement, and manage the IT Implementation project

Child Care Center (CG) Germantown - FIP Informational BLOG "Link"

  • In-Progress - Participate in development, participate in planning, budget development, & construction planning (meetings and requirements development) – ensure appropriate IT groups are consulted
  • 2009 -2010 –Develop IT project requirements and plan IT implementation project (finalize requirements, finalize SOW, build team etc)
  • TBD – Participate in construction activities (monitoring, inspections, and corrections)
  • TBD – Implement, procurement, and manage the IT Implementation project

ITV Relocation - FIP Informational BLOG "Link"

  • Analysis ongoing, Time-lines to be determined.

Library Renovation Rockville (three phases, floor 3, 2, and 1)
FIP Informational BLOG "Link"

  • Analysis ongoing, Time-lines to be determined.

Takoma Park Silver Spring Campus - General Activities
FIP Informational BLOG "Link"

  • Ongoing- Campus area planning and minor area renovation activities. Participate in planning, budget, and coordination meetings. Communicate relevant issues to IT groups and management; create strategic responses to initiatives

Rockville Campus General Activities
FIP Informational BLOG "Link"

  • Ongoing- Campus area planning and minor area renovation activities. Participate in planning, budget, and coordination meetings. Communicate relevant issues to IT groups and management; create strategic responses to initiatives

Germantown Campus General Activities
FIP Informational BLOG "Link"

  • Ongoing- Campus area planning and minor area renovation activities. Participate in planning, budget, and coordination meetings. Communicate relevant issues to IT groups and management; create strategic responses to initiatives